Client | : | Angelique International India Ltd. |
Govt. Agency | : | WAPCOS from India & MOWRAM from Cambodia M/s DMR, Faridabad was awarded the whole assignment by the Client and SHEPL team was engages in the assignment on monthly numeration basis by DMR till completion of Project. |
Location | : | Stung Tasal River near Aarol, Cambodia |
Scope of Work | : | Detailed civil design and project management, coordination during the construction stage on day to day basis. |
Salient features | : | Type: Irrigation & Flood Management Storage Scheme Irrigation Storage Capacity: 140 MCM Type of Dam: Concrete Face Rockfill Dam (CFRD), 22 m high and 700 m long is the first of its kind in Cambodia built by State of Art Technical Expertise, under dispersive soil conditions in the region. Main Spillway: 3 Nos. Bottom Outlet Gates, Size 5x5 m , Radial Gates. Auxiliary Spillway : Length 230 m, Width 30 m Main Quantities Executed: Excavation 1.25 lac cum, Rockfill 2.15 lac cum Concrete 30000 Cum |
Status | : | The construction of Dam, Spillway and Hydro- mechanical works was successfully completed in July, 2014 for irrigation purpose in the downstream area to Roleang Cherry regulator located in Kampong Speu |
Client | : | Angelique International India Ltd. |
Govt. Agency | : | Ministry of Agriculture, Republic of Mali, M/s DMR, Faridabad was awarded the whole assignment by the Client and SHEPL team was engages in the assignment on monthly numeration basis by DMR till completion of Project. |
Location | : | Nizer River Bank, Mali, Western Africa |
Scope of Work | : | Detailed Design Engineering of Pump House and project management, coordination during the construction stage on day to day basis. |
Purpose: | : | Irrigation |
No. of Pumps: | : | 4 Nos. |
Status | : | Completed |
Client | : | Angelique International India Ltd. |
Location | : | Honduras, Central America |
Scope of Work | : | Tender based Engineering Design Report on Jamastran Valley Irrigation Project. The details of the scope of work comprises of Water Diversion Structure Complex - River Diversion Structure Design, Intake Structure Design, Desander Tank with Flushing Arrangement Design, Bill of Quantities, Construction Methodology |
Project Description | : |
11 units of irrigation system are foreseen to be developed. Each unit of irrigation system will consist of collection system from the river, reservoir, pumping station, distribution up to the plots including the filtering and the control mechanism. Pump Station: Pump Station Design, Pump and Valves Specifications and Bill of Quantities, Water Delivery Network System : Civil Design of Delivery System, Pipes and valves specifications, Bill of Quantities and Construction Methodology |
Status | : | Completed within 7 days after award of Work Order. |
Client | : | Angelique International India Ltd. |
Location | : | Kudavadhoo, Guraidhoo & Villingilli - Maldives Islands |
Scope of Work | : | Detailed design and drawings consultancy services (construction stage) for laying of Domestic Water Pipe Line, Pre-Engineered Structure Buildings and miscellaneous Works for 3 Nos. Projects of Maldives Islands |
Project Description | : | Water Delivery Network System : Civil Design of Delivery System, Pipes and valves specifications, Bill of Quantities and Construction Methodology etc |
Status | : | Design part of the project has been completed and construction work is under progress. |
Client | : | Krishna Dairy Milk Plant, Vijayawada, Amdhra Pradesh |
Location | : | Krishna Dairy Milk Plant, Vijayawada |
Scope of Work | : | Preparation of Pre-feasibility Report (PFR) of Effluent Treatment Plant of Krishana Dairy Milk Plant, Vijayawada |
Project Description | : |
The existing treatment plant facility to be studied in detail with an objective to identify the issues of finding, effective disposal of wastewater and reduction of pollution in food-processing industries. 1. To examine the stability of treatment scheme adopted according to the characteristic of the waste water. 2. Characterization of composite waste water. 3. To examine the adequacy of size of treatment units as compared to quality of waste water. 4. To compare the treatment scheme with the IS Codes in practices and recommended schemes as per the PCB Guidelines. 5. To identify the disposal of final effluent. 6. Analysis of Soil investigation of the project site bore log data and trial pits to be under taken within the area at the critical locations for analyzing the soil profile and stability of soil for structural designing of the different structures 7. Designing and engineering of Civil structures as per guidelines given by PCB/ CPHEEO and direction of municipality. 8. Preparation of Detailed Project Report 9. Preparation of detailed estimation 10. Technical support for the approval of DPR from relevant authorities |
Status | : | Pre-feasibility report completed |